Hot Works Best Practice
Hot works cause an estimated 15% of UK construction fires — and most are started not by the cut or the weld itself, but by the unwatched fifteen minutes after it.
Sources: Fire Protection Association, HSE, CICAIR data — figures are indicative UK construction-sector averages.
What counts as hot works?
If it sparks, burns, melts or heats material above ambient ignition temperature, it’s hot works and it needs a permit. The confusion usually happens at the edges — the “just a quick cut” or the “it’s only a heat gun”. Those are the jobs that end up in claims reports.
Welding & cutting
MIG, MMA, TIG, oxy-acetylene cutting. Creates molten metal spatter and sustained ignition temperatures in the thousands of degrees.
Grinding & disc-cutting
Angle grinders, disc cutters, abrasive wheels. Showers of hot sparks travelling 8–10m, easily lodging in clothing and debris.
Brazing & soldering
Copper pipework, plumbing, HVAC connections. Lower temperature than welding but still ample to ignite insulation or dust.
Blow-torches & heat guns
Paint stripping, shrink-wrap, pipe thawing. Concentrated flame or radiant heat that can ignite hidden timber or voids behind plaster.
Bitumen boilers & roofing
Felt-roofing torches and hot bitumen. Responsible for a disproportionate share of serious commercial fires — often ignite timber decks under new felt.
Thermic lances & exothermic cutting
Demolition, concrete cutting. Extreme ignition risk — molten particles travel well beyond standard 10m exclusion zones.
The permit-to-work process
A hot works permit isn’t paperwork for paperwork’s sake — it’s the discipline that makes sure every person involved has consciously signed off on the same set of controls, in sequence. Skip a step and the whole chain collapses.
-
1Pre-work survey
Walk the area. Identify all combustibles within 10m — insulation, packaging, timber, dust, flammable liquids. Remove what you can. What you can’t remove, shield with fire blankets or non-combustible boards. Check voids, ducts and floor penetrations that sparks could fall into.
-
2Issue the permit
Authorised signatory only. Names of operative and fire watcher, precise location, start and end time, specific control measures. No copy-paste permits from last week — every one is for this task, this area, this shift.
-
3Sign-on
The operative signs to confirm they’ve read the permit, understand the controls, and have the PPE listed. The fire watcher signs to confirm they understand what ‘watching’ actually means and won’t leave the post.
-
4Perform the work
Fire watcher in attendance, extinguisher (CO2 or dry powder) within reach, water on standby. If any control fails — missing PPE, extinguisher moved, combustibles uncovered — work stops.
-
5Sign-off & fire watch
Work ceases. Permit signed off. Fire watch continues for a minimum 60 minutes after the last spark. In high-risk environments (roofs, voids, warehouses full of combustibles) extend to 2–4 hours or longer.
-
6Final check
Authorised person re-inspects at the 2-hour mark. Thermal imaging is worth its weight in gold here — confirms no smouldering in insulation, voids or debris before the site is left unattended.
The fire watcher — the most important job on site
Fire watcher isn’t a job for the apprentice, the nearest spare pair of hands, or someone who can “keep an eye on it while you grab a brew.” It’s a focused role with specific competencies.
The fire watcher must…
- Remain in the immediate work area throughout the task and the full 60-minute post-work watch.
- Have clear line of sight to the operative and the opposite side of any wall being cut or welded.
- Have an extinguisher in hand (CO2 or dry powder) and know how to use it.
- Carry a means of raising the alarm — radio, phone, hooter.
- Stop work immediately if any control measure fails or a new hazard appears.
- Not be assigned any other task — no lifting, no radio calls, no fetching tools. Watching is the whole job.
Before / during / after — the site check
The permit makes the plan. The check makes sure it happened.
Before you strike the arc
- Permit signed, dated and visibly displayed
- Combustibles cleared or shielded within 10m
- Voids, ducts and penetrations checked and sealed
- CO2 or dry-powder extinguisher within arm’s reach
- Fire watcher briefed, in position, nothing else to do
- Water / damping available for adjacent material
- PPE matches the task (visor, gauntlets, fire-retardant overalls)
Stop work — immediately — if…
- Wind is carrying sparks outside the protected zone
- A void or cavity is discovered mid-task
- The fire watcher is called away, for any reason
- A fire alarm sounds anywhere on site
- Permit duration has been exceeded
- Combustible material has shifted into the exclusion zone
- You smell smoke, char or hot insulation
What a hot works permit must contain
There’s no legally-mandated template — but insurers, the FPA and HSE all point to the same minimum set of fields. If your current permit is missing any of these, it’s not fit for purpose.
The three failures behind most hot-works fires
Walk through any major insurance-claim report on hot-works fires and you’ll find the same three root causes over and over.
The 60-minute shortcut
Fire watch cut short to finish the shift. Slag embedded in insulation smoulders for hours before flashover — the single biggest cause of hot-works fires in the UK.
No-one watching
Fire watcher called away “for two minutes” to help lift, collect a tool, or answer a call. Work continues. This is the scenario every insurance claim report describes.
Hidden voids
Sparks find cavities you didn’t know existed — floor voids, cable risers, false ceilings. If you can’t see behind a wall you’re cutting near, assume there’s combustible material there.
What site leaders can lock in this week
If you’re the SHEQ lead, supervisor or site manager, these are the moves that immediately lower your hot-works risk — without waiting for the next audit cycle.
- Standardise your permit template. One permit across all sites and all subcontractors. No “their version” vs “your version” — one pack, always the same fields.
- Publish a Hot Works exclusion list. Areas where no hot works are allowed under any circumstance (plant rooms, roof voids, loaded racking, storage yards). Get signage up.
- Ring-fence the fire watcher. The watcher is off all other duties for the full task plus 60 minutes. Make that explicit in your permit sign-on.
- Invest in a thermal imager. One camera per site. Mandatory on all 2-hour final checks where insulation, voids or concealed cavities are in the work area.
- Train every authorising signatory. Not just “the SHEQ manager” — anyone who might sign a permit needs formal training. Our e-learning covers exactly this.
Hot Work Training (online)
15-minute certified course with end-of-course assessment and digital certificate — for operatives, watchers and authorising signatories. Hub readers get 10% off — use code HUBHOT10 at checkout.