Build the programme.

A programme is just the job, in the right order, with sensible timings. Here’s a simple one for a bathroom refit. Read it, then answer the questions — the same thinking scales up to a whole building.

Example programme · Bathroom refit

The order of work

StepTaskTime
1Strip out the old bathroom1 day
2First fix — pipes & cables in the walls1 day
3Plaster the walls1 day (+ drying)
4Tile2 days
5Fit the suite & second fix1 day
6Seal, test & hand over1 day

Everything below is based on this programme. Read the order, then answer.

Use the programme above to answer these. Pick one answer each, then hit Mark my answers — you’ll get an explainer on every one.
Q01 1 of 5

Why does 'first fix' come before plastering?

Why: First fix (pipes and cables) has to happen before the walls are closed up and plastered - you can't easily add them afterwards.

Q02 2 of 5

Task B can't start until Task A finishes. That's called...

Why: When one task relies on another finishing first, that's a dependency - the backbone of any programme.

Q03 3 of 5

The tiling slips by two days. What's most likely affected?

Why: Tasks that depend on tiling all shift too. A slip early in the chain ripples through everything after it.

Q04 4 of 5

'Lead time' on the chosen tiles is 3 weeks. What should the manager do?

Why: If something takes 3 weeks to arrive, you order it early - or it holds the whole job up.

Q05 5 of 5

What's the point of building a programme at all?

Why: A programme sequences the work, reveals clashes before they happen, and gives everyone a finish date to aim at.